Arizona PURPA avoided-cost rates

The standard-offer rates for small generators (qualifying facilities) published by 3 investor-owned utilities we cover in Arizona: Arizona Public Service (APS), Tucson Electric Power (TEP) and UNS Electric. Checked on October 4, 2026.

UtilityScheduleSize capRate structureEffectiveChecked on
Arizona Public Service (APS)Rate Rider EPR-2, Partial Requirements Service for Qualified Facilities of 100 kW or Less (A.C.C. No. 6214, Revision No. 21); purchase terms in Service Schedule 2 (Terms and Conditions for Energy Purchases from Qualified Cogeneration and Small Power Production Facilities)Customers with an on-site QF of 100 kW-ac nameplate or less interconnected to APS's distribution grid; QFs larger than 100 kW contract under Decision Nos. 52345 and 77512.Bill credit for exported energy in $ per kWh, by season (summer = May-October billing cycles, winter = November-April) and by on-peak/off-peak hours of the customer's retail rate (shoulder-peak hours credited at the on-peak rate); separate Non-Firm and Firm rates.2024-03-082026-10-04
Tucson Electric Power (TEP)Rider-11 (R-11), Partial Requirements Service (PRS) and Purchase Rates for Qualifying Facilities (Third Revised Sheet No. 711)Published purchase rates apply to QF Customers (generator and load at the same premises) with nameplate capacity 100 kW or less; QFs over 100 kW get individually negotiated contracts under Decision No. 77513. Not available to customers on Net Metering Rider-4.Short-run avoided cost energy rates in cents per kWh, by season (summer = May-September billing cycles, winter = October-April) and by interconnection voltage (distribution vs. high voltage). Renewable QFs: flat seasonal rate by solar technology profile. Cogeneration QFs: on-peak/off-peak (summer on-peak 2-8 p.m. weekdays; winter on-peak 6-10 a.m. and 5-9 p.m. weekdays). A minimum $25.00 monthly basic service charge applies to QF Customers selling energy.2026-06-012026-10-04
UNS ElectricQualified Facilities tariffs QF-A (Full Requirements 100 kW or Less, Sheet 804), QF-B (Partial Requirements 100 kW or Less, Sheet 805) and QF-C (Optional Service Over 100 kW, Sheet 806); Fourth Revised SheetsQF-A and QF-B: QF Customers requiring 100 kW or less (QF-A buy/sell full requirements; QF-B partial requirements; both must take a standard offer rate with a demand charge). Renewable rate tables are stated for QFs with nameplate capacity below 100 kW. QFs over 100 kW contract under Decision No. 77514 (QF-C).Short-run avoided cost energy rates in cents per kWh, by season (summer = May-October billing cycles, winter = November-April) and by interconnection voltage (distribution vs. high voltage). Renewable QFs: flat seasonal rate by solar technology profile. Cogeneration QFs: on-peak/off-peak (summer on-peak 2-8 p.m. weekdays; winter on-peak 5-9 a.m. and 5-9 p.m. weekdays). QF-A nets monthly kWh and pays the purchase rate only on net deliveries.2026-06-012026-10-04

When these rates change next

Rates, eligibility and contract terms change: confirm them with the utility or the state utility commission before relying on them.