All utilities › Georgia › Georgia Power
Georgia Power Company: what it publishes for small generators (qualifying facilities) under PURPA, field by field, with the source for each. Checked on October 4, 2026.
When this may change: Annual avoided cost (Docket 4822) and solar avoided cost (Docket 16573) projections filing. Recent filings: 2022-07-29, 2023-07-31, 2024-06-07, 2025-06-27, 2026-06-26. The next one is expected around mid-2027, but no due date is stated.
Rates, eligibility and contract terms change: confirm them with the utility or the state utility commission before relying on them.
| Schedule | QF Standard Offer Contracts approved by the GPSC: Energy-Only PPA ('Standard Contract for the Purchase of Non-Firm Energy from a Qualifying Facility', available to any eligible QF); Capacity and Energy PPA and Proxy PPA (only when Georgia Power has an IRP capacity need and has issued a capacity RFP). Small customer-sited generation sells excess energy under tariff Schedule RNR-11 (Renewable and Nonrenewable Resources). Note: Not a numbered tariff sheet: the PURPA standard offer is a set of GPSC-approved pro forma contracts, with avoided costs published in an annual informational filing. RNR-11 is the tariff for small behind-the-meter generators. Source: georgiapower.com: power-purchasing-contracting-process.html · checked 2026-10-04 | |||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Docket or order | GPSC Docket Nos. 4822 (Capacity and Energy Payments to Cogenerators under PURPA), 16573 and 19279; Final Order of March 11, 2021 approved the QF Standard Offer Contracts and the avoided energy cost methodology. Current avoided-cost projections are the 2026 filing in Dockets 4822 and 16573 (filed 2026-06-26). Note: Order text from the Word version of the GPSC order (document 184685). The 2026 projections filing is PSC document 227048. Source: services.psc.ga.gov: 66319 · also: georgiapower.com: qf-definitions.html, services.psc.ga.gov: 108345 · checked 2026-10-04 | |||||||||||||||||||||
| Effective date | No single effective date: energy is paid at the hourly avoided cost under the pro forma contracts approved by the 2021-03-11 Final Order; the current avoided-cost projections were filed 2026-06-26 Note: This is the filing date of the current avoided-cost projections. Per the cover letter, they replace the June 27, 2025 projections. The contract forms and hourly-rate methodology date from the 2021-03-11 Final Order. Calendar-2026 RNR credits use the 2026 row of the June 27, 2025 filing. RNR-11 itself is effective 'With Bills Rendered for the Billing Month of January, 2023' (Original sheet). No later RNR revision was found on georgiapower.com. Source: services.psc.ga.gov: 108345 · also: georgiapower.com: RNR-11.pdf, services.psc.ga.gov: 66319, services.psc.ga.gov: 104380 · checked 2026-10-04 | |||||||||||||||||||||
| Next update | Annual avoided cost (Docket 4822) and solar avoided cost (Docket 16573) projections filing. Recent filings: 2022-07-29, 2023-07-31, 2024-06-07, 2025-06-27, 2026-06-26. The next one is expected around mid-2027, but no due date is stated. Note: The 2021 Final Order requires '20 years of annual avoided cost projections' but sets no filing date. Georgia Power's QF page refers to its 'annual avoided cost filings'. RNR-11 says the Solar Avoided Energy Cost 'is updated annually'. The filing dates come from the GPSC docket 4822 document list. Source: georgiapower.com: qualifying-facilities.html · also: services.psc.ga.gov: 66319, georgiapower.com: power-purchasing-contracting-process.html, georgiapower.com: RNR-11.pdf, psc.ga.gov: facts-docket?docketId=4822 · checked 2026-10-04 | |||||||||||||||||||||
| Size cap | Energy-Only PPA: any eligible QF (small power production QFs are 80 MW or less under FERC rules). Capacity payment: a QF over 30 MW must bid into a capacity RFP; a QF of 30 MW or less is exempt from bidding but must give notice of intent through the RFP. RNR-11: renewable resources up to 10 kW AC (residential) or 250 kW AC (commercial), with 100-250 kW AC systems limited to 125% of the prior year's peak demand; fuel cells up to 10 kW AC (residential) or 100 kW AC (commercial).Source: georgiapower.com: qualifying-facilities.html · also: georgiapower.com: power-purchasing-contracting-process.html, georgiapower.com: RNR-11.pdf · checked 2026-10-04 | |||||||||||||||||||||
| Resource types | Any FERC-certified QF: small power production (renewable such as hydro, wind or solar, plus biomass, waste and geothermal) and cogeneration. The avoided-cost projections are split into non-intermittent QFs and intermittent QFs by technology: Solar DG BTM, Solar Ground-Mounted Tracking, Solar Ground-Mounted Fixed Tilt and SE Wind. RNR-11 covers Green-e-defined renewables (solar, wind, geothermal, limited hydro, biomass) and fuel cells.Source: georgiapower.com: qualifying-facilities.html · checked 2026-10-04 | |||||||||||||||||||||
| Energy rate structure | As-available, variable hourly pricing. Energy-Only PPA monthly payment = the sum over each hour of energy delivered (grossed up for RCB Framework loss benefits, roughly 0-7% depending on interconnection level) times the Hourly Avoided Energy Rate ($/MWh) for that hour. The annual filing gives informational 20-year projections: for non-intermittent QFs by year and by season/period (peak season June-September; peak hours are weekday 9am-10pm EDT); for intermittent QFs by year and technology (profile-weighted). The QF also pays a Monthly Administrative Charge of $115 (<3 MW) or $275 (>=3 MW). RNR-11 Instantaneous Netting credits excess energy at the annual Solar Avoided Energy Cost rate plus a 4 cents/kWh Renewable Generation Adder. Note: The projections are labelled 'for informational purposes and actual payments will differ', except the RNR Solar BTM rate, which sets RNR payments. Source: georgiapower.com: QF-Standard-Offer-Contract-Energy-Only-PPA-2021… · also: services.psc.ga.gov: 108345 · checked 2026-10-04 | |||||||||||||||||||||
| Energy rates (sample cells) |
Copied as printed: a few labelled cells, not the full rate matrix. The whole schedule is linked below. Note: Items 1-3 are from the 2026 filing (PSC doc 227048). Items 4-5 are from the 2025 filing (PSC doc 223157, https://services.psc.ga.gov/api/v1/External/Public/Get/Document/DownloadFile/223157/104380). Item 6 is from RNR-11 (https://www.georgiapower.com/content/dam/georgia-power/pdfs/residential-pdfs/residential-rate-plans/RNR-11.pdf). Actual Energy-Only PPA payments use hourly avoided costs, not these annual projections. Source: services.psc.ga.gov: 108345 · also: services.psc.ga.gov: 104380, georgiapower.com: RNR-11.pdf · checked 2026-10-04 | |||||||||||||||||||||
| Capacity payment | Energy-Only PPA: no separate capacity payment. Capacity is paid only under the Capacity and Energy PPA (90% availability) or the Proxy PPA (96% availability), and only when Georgia Power has an identified IRP capacity need and has issued a capacity RFP. The 2026 filing projects avoided capacity cost of 0.00 $/kW-yr for 2027-2032 and 279.18 $/kW-yr in 2033 (non-intermittent table). Note: The capacity values are informational projections from the 2026 filing (https://services.psc.ga.gov/api/v1/External/Public/Get/Document/DownloadFile/227048/108345). Georgia Power's QF page says standalone solar QFs cannot meet the capacity contracts' availability requirements (per the 2021 order). Source: georgiapower.com: QF-Standard-Offer-Contract-Energy-Only-PPA-2021… · also: services.psc.ga.gov: 108345, georgiapower.com: power-purchasing-contracting-process.html · checked 2026-10-04 | |||||||||||||||||||||
| Contract terms | The Energy-Only PPA runs for a term of '[_____] Annual Periods from the Commercial Operation Date'. The length is left blank in the pro forma, and no maximum or menu of terms is stated. The QF may terminate on 365 days' written notice. RNR-Monthly Netting (closed legacy pilot) has a 15-year term limit, expiring no later than 2038-12-31.Source: georgiapower.com: QF-Standard-Offer-Contract-Energy-Only-PPA-2021… · also: georgiapower.com: RNR-11.pdf · checked 2026-10-04 | |||||||||||||||||||||
| Price fixity | Variable, not fixed. Energy is paid at the hourly avoided energy rate, and the GPSC's 2021 order rejected fixed-price contracts for QFs under 3 MW. RNR credits use a Solar Avoided Energy Cost set per calendar year and updated annually.Source: services.psc.ga.gov: 66319 · checked 2026-10-04 | |||||||||||||||||||||
| Schedule link | https://www.georgiapower.com/content/dam/georgia-power/pdfs/business-pdfs/industry-services/QF-Standard-Offer-Contract-Energy-Only-PPA-2021.pdf Note: Energy-Only PPA pro forma (2021). Related documents: RNR-11 tariff https://www.georgiapower.com/content/dam/georgia-power/pdfs/residential-pdfs/residential-rate-plans/RNR-11.pdf and 2026 avoided cost projections https://services.psc.ga.gov/api/v1/External/Public/Get/Document/DownloadFile/227048/108345 (ZIP containing the PDF). Source: georgiapower.com: power-purchasing-contracting-process.html · checked 2026-10-04 |
Values are copied as printed in the source. Where a value draws on more than one document, every source is listed, primary first.